Alstom 将要在印度建造一个1GW的抽水蓄能工程
在 2011-07-11 发布

Alstom将和印度的Hindustan Construction公司合作,得到了Tehri Hydro Development Corp提供的一份价值2.85亿欧元的合同,在印度Uttarakhand州的Bhagirathi河上建造一个变速抽水蓄能工程。

这个工程将是印度的第一个采用变速技术的抽水蓄能工程。Alstom在总合同中的份额达到1.8亿欧元。Kevin想通过这个工程说明,中国以及亚洲其他国家意见开始快速地大规模地建造抽蓄电站。
 

Alstom, in cooperation with Hindustan Construction Co., has been awarded a contract worth over 285 million euros by Tehri Hydro Development Corp. to install a 1 GW variable-speed pumped-storage hydropower plant on the Bhagirathi River, located in the state of Uttarakhand, India.

This will be India's first pumped-storage power plant to use variable-speed technology. Alstom's share of the contract is worth about 180 million euros. The company will supply four 250 MW variable-speed turbine and generator units and other equipment, including main inlet valves and control and protection systems. Upon completion, the plant's electricity output will provide much-needed power to the country's northern grid.